Moving begins
Updates from the summer
Framing for the offices is almost complete.
Framing, Sheetrock, and electrical on the Shop Floor is almost complete.
The concrete slab for the shop floor is nearing completion.
Exterior painting nears completion. Sidewalks around the building are also starting to be poured.
The mezanine steel for the offices has been completed.
Painting has begun.
Aerial photo taken the day that the ceiling deck was completed.
Steel is complete and ceiling panels cover the majority of the building.
The steel and roof almost complete.
Steel continued.
First steel column goes up.
The wall panels are complete.
The outer walls near completion.
The first wall goes up.
Aerial View of the finished foundation.